Unofficial independent website. Not affiliated with Lakefront Estates & Villas, Okeechobee Community Developers LLC, its developers, lenders, brokers, associations, or any related entity. Information is compiled from public records, company disclosures, official documents, news reports, and other cited sources. Errors and later changes are possible.
Public documents report major spending categories, but do not provide a complete vendor-level general ledger. Reported spending and engineer estimates answer different questions.
Last researched Sources through Oct 7, 2026Recorded-index check through Sep 24, 2026
Combined category. Marketing cannot be isolated from this figure.
Developer-reportedSources (1) ↗
Source record
Evidence behind the record
Supports
As of October 2025, the developer reported approximately $33 million in a combined category of architecture and engineering, consulting, marketing, and financing costs. Marketing is not isolated inside this category.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
≈$89.5MDerived sum of the reported categories · Oct 1, 2025
These categories may overlap and are not an audited capital stack or proof of all project spending.
DerivedSources (1) ↗
Source record
Evidence behind the record
Supports
Arithmetic sum of the four reported categories: About $35 million + About $18 million + About $3.5 million + About $33 million combined. Completeness and non-overlap are not established.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
Developer-reported spending as of October 2025
Figures reported in the December 2025 offering document
Category
Reported amount
Status
Land development
$34.59 million to about $35 million
Developer-reportedSources (1) ↗
Source record
Evidence behind the record
Supports
Land development: $34.59 million to about $35 million. Reported October 2025.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
Vertical construction
About $18 million
Developer-reportedSources (1) ↗
Source record
Evidence behind the record
Supports
Vertical construction: About $18 million. Reported October 2025.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
General conditions
About $3.5 million
Developer-reportedSources (1) ↗
Source record
Evidence behind the record
Supports
General conditions: About $3.5 million. Reported October 2025.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
Architecture and engineering, consulting, marketing, and financing
About $33 million combined
Developer-reportedSources (1) ↗
Source record
Evidence behind the record
Supports
Architecture and engineering, consulting, marketing, and financing: About $33 million combined. Reported October 2025.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
These categories are roughly $90 million if added, but the source is not treated here as proof that the list is exhaustive or non-overlapping. No total is labeled as all project spending.
About $33 million combined
Reported spent
As of October 2025, the developer reported approximately $33 million in a combined category of architecture and engineering, consulting, marketing, and financing costs.
Developer-reportedAs of Oct 1, 2025
Marketing is not isolated inside this category.
Developer-reportedSources (1) ↗
Source record
Evidence behind the record
Supports
As of October 2025, the developer reported approximately $33 million in a combined category of architecture and engineering, consulting, marketing, and financing costs. Marketing is not isolated inside this category.
Lakefront Estates CDD Limited Offering Memorandum / Official Statement
Document date
Dec 11, 2025
Source type
Official offering document
Confidence
Primary source
February 2024 capital-improvement estimates
Estimate, not money spent
Category
Estimated cost
Land acquisition
$13,900,000
Wetlands basins
$1,700,000
Earthwork
$18,357,220
Roadway construction
$30,329,955
Entrance features
$408,534
Water supply facilities
$24,607,774
Sewer facilities
$12,215,795
Stormwater facilities
$2,279,455
Electrical
$1,600,000
Landscaping / parks
$4,000,000
Professional fees
$1,100,000
Contingency
$11,049,917
Total including contingency
$121,548,650
Line items other than contingency sum to $110,498,733. The engineer narrative's pre-contingency figure of about $110,498,773 is close but not identical. A separate exhibit total of $119,776,493 is also preserved. The differences stay visible.
$121,548,650 estimate
Estimated
February 2024 master methodology materials include a project-cost estimate of $121,548,650 including contingency.
Official offering documentAs of Feb 1, 2024
Official documentSources (1) ↗
Source record
Evidence behind the record
Supports
February 2024 master methodology materials include a project-cost estimate of $121,548,650 including contingency.
Master engineer's report and capital-improvement methodology, February 2024
Document date
Feb 1, 2024
Source type
Official offering document
Confidence
Primary source
About $110.5 million before contingency
Estimated
The same engineer material describes a pre-contingency capital-improvement total of approximately $110,498,773.
Official offering documentAs of Feb 1, 2024
Official documentSources (1) ↗
Source record
Evidence behind the record
Supports
The same engineer material describes a pre-contingency capital-improvement total of approximately $110,498,773.
Master engineer's report and capital-improvement methodology, February 2024
Document date
Feb 1, 2024
Source type
Official offering document
Confidence
Primary source
$119,776,493 alternate exhibit
Estimated
A separate project-description exhibit showed a total of $119,776,493.
Conflicting sourcesAs of Feb 1, 2024
Different lighting and contingency treatment. The tables are not collapsed into one total.
Conflicting sourcesSources (1) ↗
Source record
Evidence behind the record
Supports
A separate project-description exhibit showed a total of $119,776,493. Different lighting and contingency treatment. The tables are not collapsed into one total.
Master engineer's report and capital-improvement methodology, February 2024
Document date
Feb 1, 2024
Source type
Official offering document
Confidence
Primary source
Assessment Area One / Series 2025 estimate
Estimated project cost, not a draw schedule
Improvement
Estimated cost
Wetland basins
$500,000
Earthwork
$2,400,000
Roadways
$3,959,216
Entrance features
$500,000
Water supply facilities — Described as privately funded and operated in the Series 2025 table.
$7,094,807
Sanitary sewer facilities — Described as privately funded and operated in the Series 2025 table.
$7,864,796
Stormwater management
$1,141,490
Electrical
$878,377
Landscaping / parks
$750,000
Professional fees
$1,000,000
Contingency
$2,596,369
Total — A later allocation divides estimated benefit about $17,115,516.20 residential and $11,444,538.40 commercial.
$28,560,055
The stated total is $28,560,055. The line items above add to $28,685,055. Both figures are shown. A later allocation of the stated total is about $17,115,516.20 residential and $11,444,538.40 commercial. Costs not funded by the Series 2025 bonds were expected to come from developer equity, deposits, and EB-5 loan proceeds.
More than $800 million claimed
Dated observation
A December 2025 government grant application claims more than $800 million in combined financing for the overall development. The filing does not break that figure down enough to treat it as cash already invested.
Public recordAs of Dec 10, 2025
Not treated as cash already invested.
Public recordSources (1) ↗
Source record
Evidence behind the record
Supports
A December 2025 government grant application claims more than $800 million in combined financing for the overall development. The filing does not break that figure down enough to treat it as cash already invested. Not treated as cash already invested.
Florida Job Growth Grant proposal attributed to Okeechobee Utility Authority
Document date
Dec 10, 2025
Source type
Public record
Confidence
Primary source
A combined-financing claim in this filing is not treated as cash already invested.